Metrics & Formulas
Metrics help to measure qualities.
Given below the list of Metrics tracked in each phase of Project Life Cycle.
Phase |
Derived Measure/ Metrics |
Formula |
Definition |
Project Monitoring and Control |
On Time Delivery Index (%) |
1. # Implementations completed on
time # Implementations delivered 2. # Migrations completed on time # Migrations delivered |
% implementations competed on the Implementation end date (Planned) % migrations competed on the Migration end date (Planned) |
Project Monitoring and Control |
Schedule Variance (%) |
(Actual # days to complete implementation
– Planned # of days to complete implementation) Planned # of days to complete implementation (Actual # days to complete migration –
Planned # of days to complete migration) Planned # of days to complete migration |
% variance between the planned and actual schedule for implementation % variance between the planned and actual schedule for migration |
Project Monitoring and Control |
Size Variance (%) |
(Actual Size - Estimated Size) Estimated Size |
% variance between the planned and actual size for
implementation/migration |
Project Monitoring and Control |
Requirement Stability Index (%) |
(1- (# changed requirements + # deleted + # added/# initial
requirements)) |
Provides perceptibility to the scale and effect of requirements
changes. |
Design |
Design Review Effectiveness (%) |
(#Design Review Defects / (Design Review Defects + Code Review
Defects + Unit Testing Defects + QA Testing Defects + User Acceptance Testing
)) *100 |
|
Design |
Code Review Effectiveness (%) |
(Code Review Defects / (Code Review Defects + Unit Testing Defects + QA
Testing Defects + User Acceptance Testing))*100 |
|
Project Monitoring and Control |
Effort Variance (%) |
(Actual Effort - Planned Effort) Planned Effort |
% variance between the planned and actual effort for
implementation/migration |
Project
Monitoring and Control |
Resource Utilization (%) |
(Actual Effort / Actual Variance Effort)*100 |
|
Testing |
Test Coverage (%) |
# Test Cases Executed/# Test Cases Written |
Gives an understand of what is being tested and how much is being
tested |
Testing |
Defect Leakage (%) |
(# Pre Defects/(# Pre Defects + # Post Defects))*100 |
|
Testing |
Defects Removal Efficiency (%) |
# QA Defects (# QA Defects + # Post QA Defects) |
Efficiency of QA team in unearthing defects for the Implementation
and Migration teams to remove them before UAT |
Testing |
Delivered Defects Density (Defects per CP) |
# Post QA Defects Actual Size |
% of injected defects that escaped QA to UAT |
Testing |
Design Review Defect Density |
Design Review Defects Size in Complexity Point |
|
Testing |
QA Test case review efficiency |
Test Case Review Defects Effort Spent on Test Case Reviews |
|
Testing |
QA Defect Density |
QA Testing Defects Size in Complexity Point |
|
Testing |
UAT Defect Density |
User Acceptance Testing Size in Complexity Point |
|
Testing |
Unit Testing Effectiveness |
(Unit Testing Defects/ (Unit Testing Defects+ QA Testing Defects+ User
Acceptance Testing))*100 |
|
|
Productivity (Complexity Points per Person Hour) |
Actual Size of Implementation [or]
Migration Actual effort for Implementation [or] Migration |
# of complexity points completed in 1 person hour |
|
Effort Overrun |
(Total Estimated Effort - Actual Effort on
the project) Size in Complexity Point |
|
|
First Time Right (%) |
# Implementations [or] # Migrations closed
with zero QA and post QA defects # Implementations closed |
% of Implementations/Migrations closed with zero QA and post QA
defects |
0 comments